Downtown Waterline Project

The Downtown waterline project got underway in mid-February and will continue through fall 2017.  

The project will replace outdated water lines along Main Street from Judd Parkway to Spring St., Academy St. from S. Fuquay Ave. to Falcon Dr. and behind existing buildings between Academy St. and E. Spring St.  Construction and the switch over of existing services will result in minor disruptions of service lasting a few minutes up to an hour.  

Project Update

  • Week of Feb 27th  - Pine Street Main line installation
  • Week of March 6 - Pine Street services, Oakdale Street main line installation and services
  • Week of March 13th - Start South Main Main Street main line installation

Downtown Waterline Replacement Map (Calvinjpg_Page1